It will be an understatement to say that October was a momentous month for China’s Belt and Highway Initiative (BRI). Beijing celebrated the initiative’s tenth anniversary by holding the third Belt and Highway Discussion board; across the similar time, its signature high-speed railway (HSR) in Indonesia turned operational. The launch of “Whoosh,” the Jakarta-Bandung HSR, on October 2 has been touted as a major achievement for Indonesia and level of pleasure for China’s BRI. 

Through the Belt and Highway Discussion board, Chinese language President Xi Jinping and Indonesian President Joko “Jokowi” Widodo applauded the railway line at their bilateral assembly, claiming that it was a hit and accomplished on time. As the primary HSR in Southeast Asia, the mission holds great potential for Indonesia. By way of logistics, the railway cuts down journey time between the 2 cities from three hours to below one hour and addresses congestion that prices the financial system billions per 12 months. However maybe much more vital are the alternatives that the switch of information and know-how can have for Indonesian business. 

Opening simply forward of the initiative’s tenth anniversary, the railway has been hailed as one of many BRI’s flagship initiatives. The railway has gained wide-ranging media protection and acclaim, and fairly rightly so. Nevertheless, it’s vitally essential to not conflate a profitable launch with a profitable mission. As discussions ramp up for the extension of the road to achieve Surabaya, which is roughly 700 kilometers away from Jakarta, it’s important that classes realized from the Jakarta-Bandung HSR are taken under consideration for future infrastructure initiatives.

Whereas there may be definitely no such factor as a “excellent” infrastructure mission, the problems that plagued the Jakarta-Bandung HSR stem from a recurring trait in BRI initiatives: an absence of pre-project preparation and due diligence. This important section is the place mission financiers, builders, and authorities officers undertake a spread of assessments and value determinations of the mission from monetary sustainability to environmental impacts. When completed proper, these assessments can present vital advantages to builders, officers, and communities alike, together with direct perception into the native environmental and social context, a construction for mission monitoring and reporting, and alternatives to develop and implement plans and mechanisms to handle challenges as they come up. Conversely, with out the due diligence, issues can go incorrect and might accomplish that in a short time. 

Following the choice to show down the Japanese proposal in favor of China’s bid in late September 2015, the Jakarta-Bandung HSR mission was awarded to an Indonesian-Chinese language state-owned enterprise consortium, PT Kereta Cepta Indonesia-China (PT KCIC), in early October. The frenzy was on to kick-start building on the mission – a lot to its long-term detriment. 

On the identical day the HSR was assigned to PT KCIC, Jokowi signed Presidential Regulation No.107/2015 which sought to speed up the implementation of the railway mission. In January 2016, he signed Presidential Regulation No.3/2016, which deemed the HSR a nationwide strategic precedence mission and allowed for expediting the issuing of presidency permits. Regardless of its excessive precedence, nonetheless, the mission wasn’t even included within the authorities’s preliminary Grasp Plan of Nationwide Railway. 

Three weeks in a while January 21, 2016, Jokowi attended the mission’s ground-breaking ceremony in West Java. Regardless of the ribbon reducing, the Indonesian authorities had but to subject the permits to the contractors and the builders to start building, inflicting the mission to come back to a fast halt. It will take the Indonesian Ministry of Transport an extra two months to course of the development permits for simply the first 5 km of the 142.3km railway. 

Illustrative of the push to push the HSR by, important components of the pre-project preparation had been undertaken with lightening pace. The feasibility examine, which normally takes 18 months was finalized in simply three months, and the environmental affect evaluation (EIA) which ought to take a 12 months to a 12 months and a half to finish, was completed in simply seven days. Impartial analysts in Indonesia highlighted that the EIA uncared for to incorporate key elements together with the mission’s affect on landslides, geological fault strains, and water catchments. 

All this due diligence and mission preparation falling to the wayside was no small matter to the communities that the railway straight impacted. The shortage of a complete, clear, and a community-engaged EIA course of, particularly one which was undertaken with such pace, resulted in communities in proximity to the railway line being left nearly utterly out of the loop on the mission’s improvement and impacts. 

Residents of Laksanamekar village in West Bandung had been unnoticed of the EIA course of. When blasting started on one of many railway’s tunnels, not solely had been they caught off guard however their properties started to crack and the group loss entry to artesian water. This similar state of affairs occurred in different residential areas, together with West Java’s Tipar Sari Asih housing advanced, the place tunnel blasting inflicted vital injury on properties. Moreover, because of the rushed and haphazard EIA, adjustments in land use weren’t adequately integrated within the evaluation, ensuing blocked drainage channels, disrupted waterways, and elevated flooding. 

Land acquisition and clearance proved to be one other vital hurdle within the mission’s improvement. After the issuance of presidency permits permitting building to start, which was initially slated for August 2016, PT KCIC had but to obtain and clear a majority of the land wanted for the mission. By September 2017, the consortium introduced that it had solely cleared 55 p.c of the land wanted for the railway. It will take till roughly mid-2019 – three years after the bottom breaking ceremony occurred – for the land acquisition course of to be finalized. 

On account of not solely the land acquisition challenges but in addition the impacts of COVID-19 and shoddy mission administration, the mission rapidly started to see vital value overruns. The preliminary price ticket for the railway line was $5.5 billion. That quantity rapidly ballooned within the subsequent years to roughly $7.2 billion. The mounting mission prices brought about Jokowi in September 2021 to override a earlier 2015 decree that prohibited state funds going to the railway by the signing of Presidential Regulation No.93/2021, which paved the way in which for presidency funds for use to finance the railway. 

The uncertainties surrounding funds and the mission’s sustainability don’t cease there. The announcement in 2019 that Indonesia would shift its capital from Jakarta to a brand new, however but to be constructed metropolis, Nusantara in East Kalimantan province, sparked additional considerations over the railway’s long-term viability. When the preliminary feasibility examine was undertaken in 2017, mission builders assumed that each day passenger quantity can be roughly 61,000 and even then it will take 26 years for the mission to interrupt even. With the doubtless relocation of over 1.5 million authorities staff and their households from Jakarta to the brand new capital, PT KCIC adjusted its assumptions, considerably decreasing the each day passenger demand to 31,000 – subsequently extending the timeline to 40 years to interrupt even. 

Additional highlighting the precarious state of its monetary sustainability, the Indonesian and Chinese language governments got here to an settlement that they must allocate $64.3 million yearly to only cowl the railway’s operational and upkeep prices. That is no small matter particularly because the Indonesian authorities is more and more elevating the prospect of extending the railway line to Surabaya, which is over 700 km away from Jakarta. 

With the Indonesian authorities saying on November 1 that it’s going to work with China Railway Group, one of many main shareholders of PT KCIC, to undertake a joint examine on the Surabaya extension, it’s important – particularly for native communities and stakeholders –that missteps and classes learnt from the Jakarta-Bandung HSR aren’t repeated or misplaced. 

In looking for to supply steering on how greatest to undertake pre-project planning and due diligence and as a corollary enhance mission outcomes, the Asia Society Coverage Institute developed a Belt and Highway Initiative Toolkit to help native communities and corporations engaged within the initiative to make sure that initiatives are developed to be inclusive and environmentally and socially sustainable. Out there in English, Mandarin, Bahasa Indonesia, Khmer, and Lao, the toolkit accommodates key data on greatest practices on conducting EIAs, the right way to undertake stakeholder engagement all through the lifecycle of the infrastructure mission, and what Chinese language and worldwide legal guidelines and insurance policies related to the initiatives. 